The latest sets of plans and timetables for the final phases of our redevelopment have been published and you can access them using the links below.

Meanwhile, demolition of the old school is continuing as planned, and we expect that our old South Block will be completely pulled down by the end of June.

Landscaping of the new school grounds is underway and our newly laid grass has really benefitted from the recent nice weather and is growing nicely. The seating areas at the front of school have been extended and at the rear of the school, we are hoping it won't be too long before pupils can start using our new bike sheds and basketball areas.

Gantt Chart

Diagram 1

Diagram 2

Remember, you can see the demolition progress yourself via our three web cams, here, here, and here.



Tearing Down

The demolition of the old buildings is now well under way, and our sneak photographer captured some images of the demolition of the swimming pool, and some videos of the roof removal of East Block.

It looks like we're well on our way of meeting our target of having the demolition and the landscaping of the grounds completed on time.

Thanks to the staff, and the construction crew, for their diligence and hard work throughout these busy times. Rest assured, its all much appreciated!!

Video: Demolition 1
Play Video
Video: Demolition 2
Play Video

Swimming Pool destruction


Opening Day Entertainer

New School Front Entrance



Coming Together

Block H Assembly HallMore images have arrived showing us
Block H's Assembly Hall, a classroom
in Block C, and a rendered elevation of Block D.

All casting of concrete floor slabs has been completed and all Faculties now have windows. With over 190 workers on site, work has commenced on Kitchen and Cafe areas, as well as interior decoration within Block C.

 

Block D rendered elevation

Block C classroom